Call in the ‘Arnish’ (Lewis) Hub (25/00061/PPPM) planning decision for independent national review

Petiția este adresată către
Scottish Ministers (Scottish Government)

84 Semnături

8 %
1.000 pentru ținta colecției

84 Semnături

8 %
1.000 pentru ținta colecției
  1. Început 21.11.2025
  2. Colecție albă > 5 luni
  3. Trimitere
  4. Dialog cu destinatarul
  5. Decizie
Date personale
 

Sunt de acord cu stocarea datelor mele. Pot revoca acest consimțământ în orice moment.

Petiția este adresată către: Scottish Ministers (Scottish Government)

We call on Scottish Ministers to call in planning application 25/00061/PPPM (“Arnish Hub” / “Lewis Hub”) and determine it at national level - including, if necessary, through a Public Local Inquiry - so that peatland loss, environmental impacts, cumulative effects and public objections receive full, independent scrutiny in line with National Planning Framework 4 and Scotland’s climate and biodiversity commitments.

motive

1. Overwhelming public objection, yet the project was still approved
860 of 862 public submissions objected to the Arnish Hub. Objections raised serious concerns about:

  • destruction of Class 1 peatland
  • risks to River Creed and salmonid habitat
  • impacts on red listed birds and otter habitats
  • traffic safety on the A859 and surrounding roads
  • lack of clear local economic benefit
  • missing or incomplete cumulative assessment with the HVDC link and large wind projects

Despite this, the final decision meeting involved minimal scrutiny, and key objection evidence was not meaningfully examined.
For a population the size of the Western Isles, receiving 860 objections is extraordinary and represents one of the highest levels of public opposition ever recorded for a planning application in the area.

2. Class 1 peatland and climate commitments at risk
The project would excavate approximately 480,000 m³ of peat on nationally important Class 1 peatland.
The developer’s own Biodiversity Net Gain assessment predicts a substantial net loss.
Under NPF4 and MPF4, development on peatland requires clear evidence that alternatives have been fully considered, an exceptional public benefit that outweighs impacts, and robust mitigation and minimisation.
Given the scale of peat disturbance and its climate implications, independent Ministerial examination is essential.

3. Confusion and uncertainty over the claimed economic benefit
The developer’s Socio Economic Assessment states that the project would support 17 job years in the Western Isles, which is a modelling unit, not 17 permanent jobs.
At the final decision meeting:

  • a councillor referred to “29 annual job hours” and asked if this meant 29 full time Western Isles jobs
  • officers were unable to explain the figures
  • one officer incorrectly repeated “29 job years” even though the assessment states 17 job years for the Western Isles
  • no officer could explain how job years translate into real employment or benefit

Because economic benefit was repeatedly used as a justification for approval, the lack of a clear and accurate explanation raises serious concerns about whether councillors had the information required for a sound planning decision.

4. Cumulative impacts and the industrialisation of Arnish Moor
The Arnish Hub is not a standalone development. It is the critical grid connection point for:

  • the Western Isles HVDC Link (1.8 GW)
  • major offshore and onshore wind projects such as Spiorad na Mara, Uisenis, Druim Leathann and Grimshader

Yet the Environmental Impact Assessment states that cumulative effects “cannot be fully quantified at this stage”.
This conflicts with NPF4, which requires cumulative landscape, ecological and traffic impacts to be assessed for large scale energy infrastructure, especially where multiple developments depend on a single hub.
Without a robust national level cumulative assessment, the Western Isles risk a piecemeal expansion of industrial infrastructure across Arnish Moor and surrounding areas.

5. A systemic gap between national energy policy and local planning assessment
The Western Isles HVDC Link was approved by Ofgem on the basis of expected generation from major future wind projects, most of which do not yet have planning permission.
Local planners, however, stated they could not assess cumulative impacts because these projects were “not consented”.
This inconsistency means that national infrastructure is being approved assuming large wind projects will proceed, while local planning treats those same developments as if they do not exist.
For a project involving significant peatland loss, ecological impact and community consequences, this gap undermines the level of cumulative assessment that NPF4 requires.

6. Why Ministerial call in is necessary
The Arnish Hub has long term consequences for:

  • Scotland’s climate and peatland targets
  • biodiversity and protected species
  • communities in and around Stornoway
  • the pattern of future energy development across the Western Isles

Given the gaps in scrutiny, uncertainty over key evidence (such as peat loss and employment benefit), missing cumulative assessment, and overwhelming public objection, it is appropriate and necessary for Scottish Ministers to call in this application, conduct an independent national review, and if warranted determine it through a Public Local Inquiry.
This petition is not anti renewables. It seeks transparent and evidence based decision making that respects Scotland’s climate, biodiversity and planning commitments.

Vă mulțumim pentru sprijin, Protect Hebridean Waters, Stornoway
Întrebare către inițiator

Petiție de distribuire

Imagine cu cod QR

bilețel detașabil cu cod QR

descărcare (PDF)

Informații privind petiția

Petiția a fost inițiată: 21.11.2025
Colecția se termină: 20.05.2026
Regiune: Hebridele exterioare
categorie: Mediu inconjurator

Traduceți această petiție acum

Versiune lingvistică nouă

știri

  • This is a note from the openPetition editorial team:

    The petition conflicted with clause of the terms of use and was therefore paused. The petition has since been revised, reviewed again by the openPetition editorial team, and published.
  • This is a note from the openPetition editorial team:

    The petition conflicted with clause of the terms of use and was therefore paused. The petition has since been revised, reviewed again by the openPetition editorial team, and published.
  • Temporary closure lifted

    9 ore mai de vreme
    Dear supporters,

    The petition has been revised in accordance with our terms of use. The temporary suspension has been lifted, and the petition can now be signed again.

    We thank you for your commitment!

    Your openPetition team

De ce semnează oamenii

I live here. I am appalled by the flagrant disregard for nature, community, culture heritage and the environment in the pursuit of money. There is nothing "green" about digging up tonnes of peat and erecting turbines manufactured in China using fossil fuels, balsa wood from the rainforest and slave labour in Myanmar & Africa for rare earth minerals. There is an adverse global impact, not a benefit, and the harm to the island will be irreversible. The cost will be added to our electricity bills. Shame on every councillor who voted for it.

I’m totally against the industrialisation of my home island

I’m concerned that many environmental factors have not been taken into account in this planning approval

Important to me because I do not want our Island to be turned into an Industrial behemoth, destroying our landscape and unique culture, while the Island receives very limited actual benefit.

The concerns of the local residents have not been considered. Views seem to have been ignored to pass through this decision in a speeded manner. Concerns need to be addressed in a professional way where valid issues relating to the environment, wildlife, peat, biodiversity etc. This is a special environment and unique island community. Things need to be properly considered. The recent hearing did not do this sufficiently.

Instrumente pentru distribuirea petiției.

Ai propriul site web, un blog sau un întreg portal web? Devino un susținător și multiplicator pentru această petiție. Avem bannerele, widget-urile și API-ul (interfața) necesare pentru a le integra în site-urile tale. Spre unelte

Traduceți această petiție acum

Versiune lingvistică nouă

Ajută la consolidarea participării civice. Vrem să vă facem auzite preocupările, rămânând în același timp independenți.

Promovează acum